• Stuck on a MagiCAD or Revit model? Ask engineers who design heating, ventilation, plumbing and electrical systems every day. Members can post questions, attach screenshots and project files, and get notified when someone replies.

    Застряли с моделью в MagiCAD или Revit? Спросите инженеров, которые каждый день проектируют отопление, вентиляцию, водопровод и электрику. После регистрации можно задавать вопросы, прикладывать скриншоты и файлы и получать уведомления об ответах.

    Join free / Регистрация
    1 minute · free / 1 минута · бесплатно

MEP Engineering Daikin iCM PRO Controls Up to 16 Chillers and Heat Pumps, Including Third-Party Units

Daikin iCM PRO is a new chiller plant manager that runs up to 16 Daikin or compatible third-party chillers and heat pumps, plus pumps, towers and valves, from one controller.

Daikin has replaced its intelligent Chiller Manager with iCM PRO, available since 1 November 2026, and the headline change is that it no longer insists on an all-Daikin plant room.


  • One controller handles up to 16 chillers and heat pumps, Daikin or compatible units from other manufacturers, in a single control strategy.
  • Four sizes: iCM4, iCM8, iCM12 and iCM16, with datapoint capacity from 500 to 5,000.
  • Air-cooled and water-cooled chillers, heat pumps and multifunctional units; two-pipe and four-pipe systems, seasonal changeover, heating-only or cooling-only plants.
  • Pumps, cooling towers and control valves are coordinated by the same controller.
  • Software in two layers: Daikin's validated control core plus a Niagara-based layer for project-specific customisation.
  • Flow-based sequencing looks at hydraulic demand together with unit availability, alarms, running hours and thermal load.

What it means for MEP designers
Mixed plant rooms are the normal case in refurbishment: two old chillers stay, a new heat pump goes in, and somebody has to write a sequence that makes them cooperate. A vendor controller that officially accepts third-party machines changes how we specify the plant controls package, but it also means the hydraulic schematic and the points list must be right early, because flow-based staging only works if the flow measurement and valve logic are actually designed in. The same plant-scale thinking applies to the new Airedale data centre chillers from Modine, where sequencing many units is the whole game.

Would you trust one manufacturer's controller to stage another manufacturer's chillers, or keep that in an independent BMS?

Russian version: https://bim3d.org/threads/daikin-ic...illerov-i-teplovyh-nasosov-vklucaa-cuzie.528/
 