• Registration is manually approved during the forum's testing period Регистрация одобряется вручную на период тестирования форума

Construction DFW Airport Lifts Six Prefab Modules into Place for the Terminal F Skylink Station

DFW Airport placed all six prefabricated modules (210-310 tons each) for the new Terminal F Skylink station. Terminal F's first 15 gates are due in 2027.

DFW has lifted all six prefabricated modules of the new Terminal F Skylink station onto the live Skylink guideway, doing the lifts overnight with a heavy-lift crawler crane.

Image: DFW International Airport

  • The modules weighed between 210 and 310 tons each. The heaviest is about the weight of a fully loaded Boeing 777.
  • Each lift took about eight hours. The crane came in about 60 truckloads and took nearly two weeks to assemble.
  • Terminal F is about a $4B project. Phase one opens 15 gates in 2027, and the full build is 31 gates for American Airlines.
  • It is part of DFW's $12B "DFW Forward" capital plan.

Why it matters for designers and builders
Building the station at ground level and lifting it in avoided long Skylink shutdowns on an operating people mover. Interfaces, embeds and MEP connections have to be designed so the modules can be tied in quickly once they are set.

Source: DFW International Airport, Nov 3, 2026

Have you designed MEP for modular structures lifted onto a live system? How did you handle the connections?
 
Back
Top