Modine has started producing 2 MW and 3 MW Airedale free-cooling chillers for data centres at a new 682,000 sq ft plant in Grand Prairie, Texas.
Modine announced on 11 November that commercial production of Airedale chillers has started at its new plant in Grand Prairie, Texas. The plant builds 2 MW and 3 MW chillers with free cooling for hyperscale, colocation and high-density AI data centres.
Image: Airedale by Modine. The image shows an Airedale TurboChill DCS unit, not the Grand Prairie plant.
Why it matters for designers
On data-centre jobs, the lead time for multi-megawatt chillers often decides the programme. More US capacity for 2–3 MW free-cooling units could shorten procurement. Still check delivery slots with the vendor early, since the line ramp-up is subject to the conditions Modine lists.
Source: Modine press release, 11 Nov 2026
What chiller lead times are you seeing on data-centre projects right now?
Modine announced on 11 November that commercial production of Airedale chillers has started at its new plant in Grand Prairie, Texas. The plant builds 2 MW and 3 MW chillers with free cooling for hyperscale, colocation and high-density AI data centres.
Airedale TurboChill DCS data centre chiller
Airedale TurboChill DCS chiller, vendor product image (not a photo of the Grand Prairie plant)...
- The facility covers 682,000 sq ft and is used only for data-centre chillers.
- Modine expects it to become the largest Airedale chiller factory in the group.
- The first production line started this month. Modine aims to have four 2 MW lines running by the end of the current fiscal year, depending on equipment commissioning and staffing.
- The plant runs one shift for now. Modine plans to scale up to three shifts.
- Airedale also supplies dry coolers, coolant distribution units (CDUs) and controls for data-centre cooling.
Why it matters for designers
On data-centre jobs, the lead time for multi-megawatt chillers often decides the programme. More US capacity for 2–3 MW free-cooling units could shorten procurement. Still check delivery slots with the vendor early, since the line ramp-up is subject to the conditions Modine lists.
Source: Modine press release, 11 Nov 2026
What chiller lead times are you seeing on data-centre projects right now?