MEP Engineering Stargate Abilene: 1.2 GW AI Campus as Microsoft Leases the Expansion

The Crusoe-built Stargate campus in Abilene, Texas has been capped at about 1.2 GW (eight buildings) for Oracle and OpenAI. Microsoft reportedly leases ~700 MW of expansion.

The first Stargate campus in Abilene, Texas won't grow to 2 GW for Oracle and OpenAI. They stopped at about 1.2 GW, roughly eight buildings, and Microsoft has reportedly agreed to lease around 700 MW of the remaining capacity from developer Crusoe.

Image: OpenAI/Stargate, via DCD

  • The first two buildings went live in September 2025.
  • Oracle and OpenAI say they put the extra capacity "in other locations", including a site in Wisconsin.
  • Public trackers list Crusoe as builder and Lancium as the land and power partner, with about 4 million sq ft over eight buildings.
  • The power concept is grid supply plus on-site natural gas and battery storage.

Why it matters for designers and builders
At this scale the hard problems are power and heat rejection. Liquid cooling for AI racks, on-site generation and battery storage turn a data center into a small power plant. The building shell is the easy part, and all the risk sits with the MEP and electrical design.

Source: DCD, Mar 24, 2026 and Texas Data Center Watch

Is on-site gas generation going to be standard for AI campuses, or a stopgap until the grid catches up?
 