Sizing drainage risers when branches and offsets change between floors

web3d

Administrator
Staff member
On a multi-floor plumbing layout, the soil stacks have to jog around beams and transfer zones. After those offsets are coordinated, I find the riser calculation and vent arrangement are the parts that take the most rechecking; a pipe size that looked fine on the straight run isnt the whole story once the branches move.

How do you size and model drainage risers in MagiCAD so the system stays coherent when the stack route changes?

  • Do you recalculate the full stack after every route change, or check affected sections separately?
  • How do you handle offsets and branch connections in the model so the calculation reflects the actual layout?
  • What do you include in the riser schedule to make review and coordination easier?
  • How do you coordinate vent connections with structural openings and other services?

I’d like to hear what checks have saved you from reworking stacks late in a project. If you have a repeatable workflow, please share the sequence you use.
 
I've been through this on a few multi-storey jobs where stacks had to dodge transfer beams. MagiCAD stays coherent if you treat the drainage network as MagiCAD objects from day one rather than mixing in generic Revit pipes.

I model the main soil stacks first with MagiCAD drainage tools, then add the offsets using MagiCAD fittings so the calculation engine sees the actual developed length and any capacity reduction at the jogs. After every significant route change I recalculate the full stack; checking only the affected section has bitten me when a downstream restriction or extra branch flow appeared later.

Branches get connected with MagiCAD connection commands so flows are assigned correctly. Offsets are modelled with the real fittings and slopes; MagiCAD then uses those in the hydraulic calc instead of assuming a straight vertical run.

In the riser schedule I include stack ID, floor levels, DN, calculated flow, number of connections per floor, vent size/type, and a short note on any offset. That makes review and coordination with structure much quicker.

Vents are modelled as MagiCAD pipes as well. I run the drainage/vent calc, then clash-check the vent connections against structural openings and other services early (MagiCAD collision or Navisworks). The checks that have saved me late rework are: verifying MagiCAD connections after every offset, looking at the calculation report for flow or venting warnings, and confirming no accidental reverse grades crept in.

Typical sequence I repeat: rough-out stacks, coordinate with structure, model accurately in MagiCAD, connect all branches, full calc, size adjustments, generate schedules, clash check, then recalc if anything moves. Once that loop is in place the system stays consistent even when the route changes.
 